Project Schedule Management Plan

Subject: Tech & Engineering
Pages: 3
Words: 582
Reading time:
3 min
Study level: Undergraduate

The project schedule management plan covers all the work that has to be done to deliver the project on time. Specifically, the project concentrates on the following objectives: the creation of RFP, assessment of vendors, creation of a high-level implementation plan, and procurement and installation of new server and software. This paper consists of the project activity list, the network diagram, and the project sequencing and critical path table.

Schedule Management Approach

The project manager has the overall authority and responsibility for successfully completing this project. The project team will consist of technical, legal, and finance teams, supply management, and regulators. The project manager will work closely with all the resources to prepare the project schedule. The duration of each of the activities was estimated using the expert judgment method, which relies on information from experts knowledgeable in particular areas.

Activity List

Table 1 covers all the activities involved in the reaching the main objectives of the project, such as the creation and review of RFP, selection of vendors, signing a contract, creation of an implementation plan, and contract execution.

Table 1. Project Activity List.

WBS ID Activity Name Predecessor WBS ID Activity Duration (Days)
1.1 RFP drafts 7
1.2 Finance team review 1.1 13
1.3 Legal team review 1.1 21
1.4 Meetings with vendors 1.2, 1.3 4
1.5 Identification of vendors 1.4 20
1.6 Vendors complete a proof of concept and a demo of their solutions 1.5 70
1.7 Qualitative and quantitative assessment 1.6 10
1.8 Final selection of vendors 1.7 1
1.9 Contract negotiations 1.4 105
2.0 Final draft of a contract 1.8 1
2.1 Review of a contract 2.0, 1.9 21
2.2 Signing a contract 2.1 1
2.3 Implementation plan development 2.2 21
2.4 Procurement of new equipment and software 2.3 140
2.5 Accessibility SME work 2.4 5
2.6 Security Technical Install SME work 2.5 6
2.7 Equipment installation 2.6 35

Network Diagram

A network diagram is a graphical representation of a project’s schedule, including its main tasks and their duration. Nodes represent tasks, and arrows unite the two sequencing events. Above each node, the time duration of an activity is presented. The critical path is the sequence of activities that determines the overall length of the project (Froeb, McCann, Shor, & Ward, 2015). In project management, a network diagram is a helpful tool used in project planning and tracking. Figure 1 shows the network diagram developed on the basis of Table 1. The critical path of the project has been highlighted to show the overall duration of the project. It can be seen that some activities do not follow the critical path, and there are multiple paths of work being done.

Network diagram.
Figure 1. Network diagram.

Project Sequencing and Critical Path

The critical path consists of activities 1.1, 1.3, 1.4, 1.9, 2.1, 2.2, 2.3, 2.4, 2.5, 2.6, and 2.7. The total duration of the project is thus equal to 366 days. However, the duration of the project that ends at stage 2.1 when the contract is signed is equal to 159 days or approximately five months, as has been required by Chief Gravill. Table 2 shows how the activities are sequenced in the critical path and another activity path with a shorter duration.

Table 2. Project Activity Sequencing and Durations.

Activity Path Sequence Total Duration Critical Path Y/N
1.1, 1.3, 1.4, 1.9, 2.1, 2.2, 2.3, 2.4, 2.5, 2.6, 2.7 366 Yes
1.1, 1.2, 1.4, 1.5, 1.6, 1.7, 1.8, 2.0, 2.1, 2.2, 2.3, 2.4, 2.5, 2.6, 2.7 355 No

Reference

Froeb, L. M., McCann, B. T., Shor, M., & Ward, M. R. (2015). Managerial economics: A problem solving approach (4th ed.). Boston, MA: Cengage Learning.